Zhuhai-Zhaoqing HSR Xijiang Bridge Deep-Water Piles

Zhuhai-Zhaoqing HSR Xijiang Bridge Deep-Water Piles

客户
China Railway Group
地点
Zhuhai, Guangdong, China
完工日期
2024-06-01

112 bored piles of 3m diameter, pile depth 107m, located in approximately 30m-deep water in the Xijiang River, a typhoon-prone area.

项目挑战

Deep-water foundation construction (water depth ~30m), typhoon-prone zone, and strict environmental protection requirements in a designated ecological conservation area.

解决方案

Steel casings plus 6 large rotary drilling rigs for single-pass drilling, using a zero-discharge slurry system with GPS positioning to ensure pile position accuracy.

项目成果

Average 10 days to complete a single deep-water pile, zero environmental incidents, all piles passed ultrasonic testing with 100% compliance.