NEOM Mega City Infrastructure Pile Foundation

NEOM Mega City Infrastructure Pile Foundation

客户
NEOM Development Authority
地点
NEOM, Saudi Arabia
完工日期
2024-07-01

Underground parking and light rail tunnel pile foundation works for NEOM zero-carbon city, with pile depths of 60-90m and diameters of 2.0-2.5m.

项目挑战

Sandy strata prone to hole collapse, extremely strict zero-carbon construction standards, and tight project deadlines.

解决方案

Deployed 10 high-performance rotary drilling rigs (including high-capacity XR600E units), combined with steel casings and high-quality slurry wall protection technology.

项目成果

Achieved a daily average of 3 piles per rig, completing the project 2 weeks ahead of schedule despite starting 1 month late, demonstrating the exceptional performance of Chinese rotary drilling equipment in extreme environments.